Securing safe fuel storage:                                           As these are mandatory facilities for airports, many efforts were made for
          establishing fuel storage facility and building pipes                 maximum effect. As in Phase 3, double suction centrifugal pumps were used for
          Given rising aviation demand, Phase 4 reviewed the capacity for fuel storage,   stability and compatibility. The earth foundation was used for the storage tank
          created an expansion plan, and conducted construction for fuel storage facilities   while the concrete ringwall foundation was implemented to provide stable support
          and pipes. A new fuel pipeline was installed to serve areas such as the Terminal 2   for the load on the side plates of the storage tank. Additionally, the most high-

          apron, the northern remote apron, Apron 2, and the cargo apron. 4 hydrant pumps   quality material, A516 Gr.60, was selected for the storage tank plates, considering
          and 4 storage tanks for additional fuel supply were also added. A new monitoring   factors such as strength, post-weld heat treatment, and minimum thickness.
          system was built to integrate and link the fuel storage facility and new facilities.   For pipes, heavy duty paint was selected to prevent corrosion of the ground pipe




          224
          224                                                                                                    The 30-y ear His t ory of Incheon Airport Cons truction                                                                                                                                           225
                                                                                                                 The 30-year History of Incheon Airport Construction
   221   222   223   224   225   226   227   228   229   230   231