                                                                                     Connecting light and energy


                                                                                     establishing electrical infrastructure











                                                                                     Providing more power: establishing power grid for Phase 4
                                                                                     It was mandatory to build power infrastructure in the northwestern area of
                                                                                     Yeongjong Island and expand the Incheon Airport’s power grid taking into
                                                                                     account the mid- and long-term development plan including the nearby areas. It
                                                                                     was decided that Main Substation C with 2 transformers would be built during

                                                                                     Phase 4 in addition to existing Main Substations A and B. The implementation
                                                                                     method was coordinated with KEPCO, the power provider. It was agreed that
                                                                                     KEPCO would be responsible for constructing and operating Main Substation C,
                                                                                     Eulwang Substation, and transmission lines, while IIAC would provide the site for

                                                                                     substation and transmission lines. The construction for Main Substation C started
                                                                                     in November 2020 and was completed in April 2023. The power grid was tripled
                                                                                     by completing the power provision system that connects the Main Substations
                                                                                     A, B, and C. This was an unprecedented achievement not only domestically but

                                                                                     also internationally. Incheon Airport secured the power supply capacity for future
                                                                                     development and removed the blackout risk by creating multiple transmission
                                                                                     systems. IIAC applied eco-friendly switch-gears on 25.8kV for substations for
                                                                                     extra-high voltage, improving the power efficiency by 15% and facility lifecycle

                                                                                     by more than 20%.