During construction, the management building and facility building were interfere with the existing operation. However, IIAC was able to complete the
placed separately to prevent odors from affecting the office area. Additionally, construction seamlessly based on its flexible process management and project
underground structures were built simultaneously to accommodate future management capability.
expansions, and the biological reactor facilities were designed for phased
installation, with additional space secured for potential expansion. In the civil Providing water and energy: laying piping for outside plant
engineering section, efforts were made to improve weak ground conditions. The utility pipes for Incheon Airport have 5 types including medium temperature
Careful attention was given to selecting the right engineering method and hot water, cool water, feed water, greywater, and LNG. Phase 4 built a plan for
implementing waterproofing measures, considering the specific characteristics of additional piping amounting to about 7.4 km considering future water demand. To
the water treatment facility structures. In the mechanical section, the focus was supply water 24/7 without any interruptions, it designed more than 2 water supply
on facility automation. Notably, the key Sequencing Batch Reactor (SBR) process sources. The second pipe will provide water even if the first gets interrupted. It
was integrated with a Programmable Logic Controller (PLC) system to enable made a loop by connecting pipes at Power Buildings A, B, Terminal 1, Concourse,
automated control. Efforts were made to overcome the image as an unpleasant Terminal 2, the 2nd Joint Complex, and Power Building C. Also, outside pipes
facility and create an exterior that blends well with the nearby environment. IIAC for utility were connected to pipes for the aircraft maintenance garage, parking
utilized various materials including steel, natural stone, and wood for a better lot, and northern support center. The project was conducted from June 2021 to
appearance and created green areas nearby. September 2023 with a budget of KRW 11.1 billion.
The greywater facility construction was difficult as it was important that it not