Ensuring safe landings:
                                                                                                     establishing instrument landing system for
                                                                                                     Runway 4
                                                                                                     The Instrument Landing System (ILS) is a wireless marking
                                                                                                     to instruct aircraft of their vertical/horizontal location and
                                                                                                     distance to the landing point, making sure aircraft land safely

                                                                                                     in any weather conditions. ILS is composed of a localizer,
                                                                                                     glide path, inner markers, middle markers, and outer markers.
                                                                                                     It was required to satisfy all legal criteria before operations.
                                                                                                     CAT-III was mandatory for normal operations of Runway 4.

                                                                                                     It means that it should be possible to takeoffs and landings
                                                                                                     in the southern and northern part of the runway even in low
                                                                                                     visibility of 75 meters. The issue was frequency interference
                                                                                                     from the aircraft on the taxiway of Runway 4.

                                                                                                     To address the issue, an investigation of the external
                                                                                                     electromagnetic environment was conducted to identify signal
                                                                                                     blind spots. Precise adjustments to the equipment were made,
                                                                                                     normalizing azimuth SDM signals. Additionally, abnormal

                                                                                                     signals from the glide slope equipment were resolved through
                                                                                                     antenna calibration. As a result, Runway 4 passed the ILS
                                                                                                     CAT-III flight test in March 2021 and the flight test for the
                                                                                                     flight lighting facility in April. On June 17, 2021, the operation

                                                                                                     of Runway 4 successfully started.

















 212           PART.4 | Achieving the 100-million-passenger era | Phase 4 construction project                                                      213