Page 194 - 인천국제공항 4단계 건설사업 건설지 [화보집 영문]
P. 194
02
Expanding parking
facilities to meet
passenger demand
Accommodating more vehicles:
building T2 long-term parking lot
The T2 long-term parking lot construction project was carried out based on a
traffic characteristics survey and demand forecast. During the design phase,
changes in the operational environment were actively considered. To improve
passenger convenience, parking spaces were moved indoors, and indoor
waiting areas and boarding zones were installed to enhance convenience and
comfort. To accommodate trends in vehicle diversification and larger car sizes,
all parking spaces were designed to meet expanded size standards, improving
user convenience. Additionally, the appropriate ceiling heights and aisle widths
were secured to ensure the parking lot could accommodate a variety of vehicles,
including vans and imported cars. The construction of the T2 long-term parking
lot began in February 2020 and was completed in December 2021, resulting in the
addition of 3,778 parking spaces across an area of 145,700 square meters.
192 The 30-year History of Incheon Airport Construction 193