screen doors (PSDs) were upgraded to accommodate the 4-car trains. Observation The extension of the BHS and shuttle train linked Terminal 1, the Concourse,
elevators, direct escalators, and inclined moving walkways were installed for main and Terminal 2 to ensure the smooth operation of the airport and minimization of
facilities including Terminal 2, Transportation Center 2, and auxiliary buildings passenger confusion.
from 2014, and a central control system was built. Regarding boarding bridge
installations, beginning in 2015, 64 boarding bridges and 42 PC-AIR units (aircraft
heating and cooling systems) were installed, primarily at the Terminal 2 apron.