BHS and shuttle train that

          facilitate movement of cargo


          and passengers
















          Construction of the BHS in Phase 3 involved linking and
          expanding the BHS of Terminal 1 and the concourse with
          the BHS of Terminal 2. Based on principles of simplicity,

          reliability, and easy maintenance, Incheon Airport designed
          the Phase 3 BHS and began installation in May 2015. The new
          BHS had multi-layers with advanced facilities and usability
          including lighter trays, Early Bag Storage (EBS), Empty Tray

          Storage (ETS), and a Tab Return System (TRS). For smooth
          operation, it integrated the BHS systems and built the BHS
          Operation Center (BOC).
          The shuttle train was introduced during Phase 2 and

          expanded in Phase 3. 2 shuttle train lines were installed in the
          underground tunnel between Terminal 2 and the Concourse,
          with 2-car trains operating on the route. The shuttle train
          from Phase 2, initially composed of 3 cars, was upgraded to

          4 cars by adding an additional car. To support operations, the
          maintenance depot was expanded, including light maintenance
          tracks and departure inspection tracks, and the platform




          130                                                                                                    The 30-year History of Incheon Airport Construction                                                                                                                                               131