Installing machinery and

          electricity for 24-hour operations



























          To create an airport that runs 24/7, Phase 3 built machinery and electricity
          facilities. For machinery, absorption refrigerating machines, turbo refrigerators,
          conditioning equipment, and automatic control systems for Terminal 2,
          Transportation Center 2, and auxiliary buildings were installed. Machines and

          facilities inside and outside major buildings offered stability and safety with
          dual/triple installation. It also actively utilized new and renewable energy
          including thermal energy and heat circulation. New machinery was integrated
          with the existing automatic control system. The fueling facility was linked to the

          existing control system. For electricity, the focus was on stability, reliability, eco-
          friendliness, convenience, economic efficiency, and scalability for power grid
          facilities. Incheon Airport built a Supervisory Control Data Acquisition (SCADA)
          system and 22.9kV distribution infrastructure for stable power supply and linked

          this to major facilities. It introduced the Closed Transition Transfer Switch (CTTS)
          and built an emergency power generation system including the Power Building C
          to improve reliability.




          134                                                                                                    The 30-year History of Incheon Airport Construction                                                                                                                                               135