Completing

          Phase 3 in 9 years





























          Before Phase 3 opening, IIAC convened a Terminal 2 operation preparation
          council at the end of 2015 and confirmed the master plan for operations in June
          2016. It also created an internal/external collaboration system for successful

          operations. More time and effort were required to prepare for Phase 3 operations
          as many systems and facilities were added. The comprehensive commissioning
          started in March 2017 in earnest, and most parts were completed in August
          2017. Incheon Airport ran the trial system without stopping operations to prove a

          smooth transition and prepare for emergencies. The Phase 3 grand opening was
          held on January 18, 2018, before the 2018 Pyeongchang Winter Olympic Games.
          Phase 3 was completed after 9 years, involving 93,000 people and a budget of
          KRW 4.93 trillion, transforming Incheon Airport into a luxury airport with cutting

          edge technology. In October 2017, Incheon Airport was ranked first for a twelfth
          consecutive year at the Airport Service Quality Awards, proving its status as the
          best airport in the world.




          138                                                                                                    The 30-year History of Incheon Airport Construction                                                                                                                                               139