Page 112 - 인천국제공항 4단계 건설사업 건설지 [화보집 영문]
P. 112
Making an eco-friendly airport,
where nature, technology,
and culture harmonize
Passenger Terminal 2 curbside. Considering the congestion at Terminal 1’s curbside,
The construction of Passenger Terminal 2 was the core part Terminal 2 placed its route bus terminal on the first basement
of the Phase 3 project. Terminal 2 consists of 2 underground level of Transportation Center 2, reducing curbside congestion.
stories and 5 above-ground stories, with an overall design This created a close-range, integrated public transportation
inspired by the image of a soaring phoenix. It integrates system, differentiating it from Terminal 1. During the Terminal
nature-friendly (Green), eco-friendly (Eco), and cutting- 2 construction, the fast-track method, which combines design
edge technology (Smart) concepts with traditional Korean and construction phases, was employed along with full-
culture (Culture) to reflect the identity of Incheon Airport. responsibility supervision. Several innovative construction
The terminal's design incorporates curves both inside and techniques were also introduced. In the structural and exterior
outside, complementing the existing facilities from Phases work, the Mega Truss Travelling method was used to install the
1 and 2, while creating a unique, differentiated space. A massive roof trusses, while the large-scale louver system was
streamlined transfer system was established by focusing on applied for the first time in Korea to create a visually stunning
transfer flows and specialized amenities, ensuring fast and 3-dimensional, curved ceiling in the check-in area. Above all,
convenient passenger transfers. Additionally, commercial IIAC focused on rigorous interface management to ensure the
facilities were concentrated near the departure hall to enhance project stayed on schedule. As a result, the construction of
passenger convenience and maximize spatial efficiency. Terminal 2 was successfully completed on time in June 2017.
In particular, route bus stops were installed and operated
110 111