Introducing 3-dimensional

                                                                                     design technology (BIM) to


                                                                                     minimize interface conflicts














                                                                                     The Phase 3 construction project implemented various strategies to efficiently
                                                                                     manage interfaces between individual projects. In 2013, the airport introduced
                                                                                     building information modeling (BIM), a technology that combines construction
                                                                                     information into 3-dimensional models, allowing for more effective prevention

                                                                                     of potential conflicts and interface issues during construction. During the initial
                                                                                     stage of introduction IIAC identified areas likely to encounter interface conflicts
                                                                                     and created BIM data for these areas. This data was used to review potential
                                                                                     clashes between different project packages and actively support decision-making

                                                                                     regarding conflict resolution. Over the next 3 years, Incheon Airport systematically
                                                                                     developed and applied BIM technology, establishing a sustainable process that
                                                                                     included pre-construction reviews, project support, and the digitalization of
                                                                                     deliverables. This proactive approach allowed the airport to efficiently prevent

                                                                                     interface conflicts throughout the construction phase.
                                                                                     In recognition of these efforts, Incheon Airport received the Award from the
                                                                                     Minister of Land, Infrastructure, and Transport, the highest honor at the BIM
                                                                                     Competition in September 2016, highlighting its achievements to external

                                                                                     audiences. The BIM technology, first introduced during the Phase 3 project,
                                                                                     has since evolved into a core element of Incheon Airport construction process,
                                                                                     continuing its application into the Phase 4 project.