For the system integration tests, 14 groups were assigned to          This large-scale national project involved an investment of
               conduct 60 scenarios, ensuring full interoperability between          KRW 2.9 trillion. As a result of the expansion, the number of

               information and equipment systems. Similarly, the integrated          runways increased from 2 to 3, and the passenger apron area
               trial operations was carried out by 5 groups following 49             grew from 1.267 million square meters to 2.443 million square
               scenarios under conditions identical to real-world operations.        meters. The cargo terminal also doubled in size, reaching
               After these rigorous preparations, IIAC held the grand opening        129,000 square meters. The project not only expanded the

               ceremony for the Phase 2 construction project on June 20,             airport’s size but also improved its services. From 2005 to 2007,
               2008.                                                                 Incheon Airport was named the “Best Airport in the World”
                                                                                     for 3 consecutive years by the Airports Council International
                                                                                     (ACI), demonstrating its status as one of the world’s top-tier

                                                                                     airports in terms of both facilities and services.












































 98            PART.2 | Bringing the world together in a larger space | Phase 2 construction project                                                 99
   96   97   98   99   100   101   102   103   104   105   106