Phase 2 opening to become                                             The Phase 2 construction project, which began in 2002,

          the world’s best airport                                              entered its final stages in 2008. Just like the Phase 1 opening,
                                                                                IIAC formed a task force to prepare for the Phase 2 opening,
                                                                                committing itself to system integration tests and integrated
                                                                                trial operations. A key focus of the Phase 2 opening was to
                                                                                seamlessly integrate the new systems with the existing Phase 1

                                                                                airport operation systems. To ensure smooth integration, IIAC
                                                                                allocated sufficient time for trial operations and verified the
                                                                                soundness of each system in stages.

















































          98                                                                                                     The 30-year History of Incheon Airport Construction                                                                                                                                                99