The core task:                      The expansion of Terminal 2 was the centerpiece of the Phase 4 construction project. On


            Terminal 2                          November 19, 2019, a ground-breaking ceremony was held at the Terminal 2 construction site,
                                                marking the start of this extensive work. Through Phase 4, the wing-shaped spaces on both the
            expansion                           east and west sides of Terminal 2 were extended. This complex task involved demolishing the

                                                end walls, installed at the far ends of Terminal 2 during Phase 3, and seamlessly attaching new
                                                structures—a feat requiring immense precision, as active operations were taking place just 5-6
                                                meters away in adjacent areas. The project included electrical, mechanical, and communication

                                                work within an operating terminal, requiring meticulous planning to avoid passenger disruption
                                                from noise or vibrations and to protect the interests of resident agencies and commercial facilities.
                                                Construction was carried out mainly at night, with schedules carefully coordinated through
                                                discussions with stakeholders.

                                                As a result of the expansion, each wing of Terminal 2 was extended by 750 meters from 440
                                                meters, adding 340,000 square meters of space—equivalent to 48 soccer fields. With an increased
                                                capacity of 29 million passengers annually, Terminal 2’s total capacity rose from 23 million to
                                                52 million. Combined with Terminal 1’s 54 million, Incheon Airport’s total passenger capacity

                                                expanded from 77 million to 106 million. Incheon Airport became the world’s first airport to
                                                operate two terminals each capable of handling over 50 million passengers annually.