Constructing Concourse,

          a new landmark




















                                                                                                                   Concourse was the most prominent
                                                                                                                   facility among the architectural
                                                                                                                   projects of Phase 2. Covering a total

                                                                                                                   area of 167,000 square meters, it was
                                                                                                                   built on the north side of Terminal
                                                                                                                   1, with 2 underground stories and 5
                                                                                                                   above-ground stories. The Concourse

                                                                                                                   is 40 meters wide, 918.4 meters long,
                                                                                                                   and 34.2 meters high. In response
                                                                                                                   to changing aviation demand and
                                                                                                                   a comprehensive review of aircraft

                                                                                                                   parking plans, 30 fixed boarding
                                                                                                                   bridges were installed: 5 for Code F
                                                                                                                   aircraft, 12 for Code E, and 13 for
                                                                                                                   Code D.











          86                                                                                                     The 30-year History of Incheon Airport Construction                                                                                                                                                87