tower is a steel structure with 1 underground
          story and 12 above-ground stories, standing

          about 65.09 meters tall. The exterior features
          aluminum panels and a glass curtain wall,
          designed to align architecturally with Concourse
          and harmonize with the overall airport aesthetic.

          The construction was divided into 2 phases.
          First, the underground portion of the control
          tower was connected to the north section of
          Concourse. Afterwards, after the package work

          for structural framework, finishing work, and
          auxiliary facilities of Concourse began, the
          remaining construction, including the upper
          structure was conducted in June 2006. Despite

          various challenges, the new apron control tower
          was successfully completed. It was recognized
          as a model example of curtain wall construction,
          drawing significant attention from industry

          professionals.


























          84                                                                                                     The 30-year History of Incheon Airport Construction                                                                                                                                                85