Connecting spaces:
installation of passenger boarding bridges
To ensure passengers’ convenient boarding, mobile and
connecting boarding bridges were installed. First, IIAC
reviewed problems and areas of improvement identified during
operations of boarding bridges from Phase 1 to 3 and reflected
them into the design.
The operating method of the boarding bridges, the apron
drive type, used in Phases 1 to 3, was chosen for forward and
reverse movement, as it is easy to drive. For the ascent and
descent movement, a hydraulic type was selected, which is
consistent with the concept used for Terminal 1, Concourse
A, and Terminal 2. The exterior was designed to harmonize
with the first 3 Phases, featuring glass walls that allow natural
light, and the connecting bridges were also designed with the
same approach. Starting in April 2022, 57 mobile boarding boarding bridges to be connected remotely from the control
bridges and 43 connecting boarding bridges were installed in room by viewing a screen, eliminating the need for on-site
alignment with the construction of the attached gates. While manual operation. Additionally, the compatibility of the
surging raw material prices risked delaying completion during boarding bridges was improved to optimize aircraft movement
the subcontractor selection process, production of the mobile paths, allowing larger aircraft like the A380 to dock at more
boarding bridges was completed in November 2023, ahead of locations compared to the Phase 3 construction project.
schedule by using 2 production plants. Meanwhile, alongside the boarding bridge installation, aircraft
The mobile boarding bridges of the Phase 4 construction ground support equipment was also established. 37 units of
project feature a remote docking system, which enables the preconditioned air systems (PC-Air) and 36 aircraft public
water systems (PWS) were added, with optimal facilities
deployed based on an analysis of the strengths and weaknesses
of existing equipment. Moreover, the central control system,
integrated with the Phase 3 central control system, was newly
established.