Connecting spaces:
               installation of passenger boarding bridges
               To ensure passengers’ convenient boarding, mobile and
               connecting boarding bridges were installed. First, IIAC
               reviewed problems and areas of improvement identified during
               operations of boarding bridges from Phase 1 to 3 and reflected

               them into the design.
               The operating method of the boarding bridges, the apron
               drive type, used in Phases 1 to 3, was chosen for forward and
               reverse movement, as it is easy to drive. For the ascent and

               descent movement, a hydraulic type was selected, which is
               consistent with the concept used for Terminal 1, Concourse
               A, and Terminal 2. The exterior was designed to harmonize
               with the first 3 Phases, featuring glass walls that allow natural

               light, and the connecting bridges were also designed with the
               same approach. Starting in April 2022, 57 mobile boarding             boarding bridges to be connected remotely from the control
               bridges and 43 connecting boarding bridges were installed in          room by viewing a screen, eliminating the need for on-site
               alignment with the construction of the attached gates. While          manual operation. Additionally, the compatibility of the

               surging raw material prices risked delaying completion during         boarding bridges was improved to optimize aircraft movement
               the subcontractor selection process, production of the mobile         paths, allowing larger aircraft like the A380 to dock at more
               boarding bridges was completed in November 2023, ahead of             locations compared to the Phase 3 construction project.
               schedule by using 2 production plants.                                Meanwhile, alongside the boarding bridge installation, aircraft

               The mobile boarding bridges of the Phase 4 construction               ground support equipment was also established. 37 units of
               project feature a remote docking system, which enables the            preconditioned air systems (PC-Air) and 36 aircraft public
                                                                                     water systems (PWS) were added, with optimal facilities
                                                                                     deployed based on an analysis of the strengths and weaknesses

                                                                                     of existing equipment. Moreover, the central control system,
                                                                                     integrated with the Phase 3 central control system, was newly
                                                                                     established.