Building the framework: expansion structure & finishing work
          The structural and finishing work was divided into east and west sections for order placements. To minimize interference

          among project packages, the exterior and finishing processes were combined, and the sections were separated. Despite issues
          like a sharp rise in raw material prices during construction, IIAC prevented the worst-case scenario of halting construction
          through better communication with contractors and contract adjustments to reflect price fluctuations. As a result, the
          underground structural work was completed in March 2022, the above-ground structural work in November, and the exterior

          and roofing work began in July 2022.





















































          148                                                                                                    The 30-year History of Incheon Airport Construction                                                                                                                                               149