Preparing for the 100-million-passenger era

            Phase 4                            Construction of Runway 4 and Terminal 2 expansion             2017~2024



            From construction planning to project management      million passengers annually, covering an area of 734,000 square meters.
            Accommodating 100 million passengers annually was the original   Another critical task was the construction of Runway 4, essential for
            goal outlined in 1992, when plans for the Seoul Metropolitan Area’s   ensuring stable airport operations. Incheon Airport embarked on this

            new airport were first conceived. That ambitious target was now on   new phase with a well-organized construction plan and thorough project
            the horizon. As Phase 3 construction neared completion at end-2015,   management, aiming to establish itself as a global mega hub.
            the airport began to prepare for the future to keep pace with rising
            aviation demand. A primary goal was the expansion of Terminal 2,   Construction of key Phase 4 airport facilities

            increasing its capacity from 23 million passengers per year to 52   The Phase 4 project focused on both airside and landside areas, including
            million. With Terminal 1 included, the total capacity would reach 106   the construction of Runway 4 and the expansion of Terminal 2. The