Preparing the site



               Offshore site preparation work
               After the initial master plan was approved, the
               government held the ground-breaking ceremony for
               Incheon Airport on November 12, 1992, taking on

               the Phase 1 construction project. Site preparation
               was conducted first. Most of the site was prepared by
               reclaiming the tidal flats between Yeongjong Island and
               Yongyu Island. Next, sea wall construction, dredging,

               land reclamation, and ground improvement operations
               were conducted to stabilize the ground. Building an
               airport on an island in the middle of the sea was not
               an easy task. It took more time and effort than general

               construction projects, as all materials, manpower, and
               equipment had to be transported by sea.











                                                                                                           The seawalls served as both a structure for reclamation

                                                                                                           and the boundary of the airport site. They were
                                                                                                           positioned to maximize the site’s potential for future
                                                                                                           expansion, while also considering the overall form of the
                                                                                                           site. The dredging and reclamation process minimized

                                                                                                           environmental impacts by using a pump dredger to suck
                                                                                                           sand and seawater from the surrounding area and then
                                                                                                           deposit it in the target area through sand discharge pipes.




 38            PART.1 | Opening new sky route on Yeongjong Island | Phase 1 construction project                                                     39