Page 188 - 인천국제공항 4단계 건설사업 건설지 [화보집 영문]
P. 188

03


          Improving operational

          efficiency


          maintenance of existing runways



          The Phase 4 construction project also included maintenance of
          aging runways. In coordination with the opening of the newly
          built Runway 4, maintenance work was carried out sequentially

          across the existing runways in the order of Runway 3, Runway
          2, and Runway 1. This was not merely a repaving project,
          but involved additional improvements to enhance operational
          efficiency. For example, a right-angle taxiway was added to

          Runway 2 and RETs were installed on Runway 1.



































          186                                                                                                    The 30-year History of Incheon Airport Construction                                                                                                                                               187
   183   184   185   186   187   188   189   190   191   192   193