Laying solid foundations: site preparation
          For the airside area, the existing airport facilities operated 24/7, covering a vast

          area of diverse ground conditions. Additionally, interference with existing Phase 1
          to 3 facilities had to be considered. As a result, a comprehensive site preparation
          plan was established taking into account various surrounding factors. The target
          area for the Phase 4 airside construction project included land where ground

          improvement had been prepared during the Phase 2 construction. However, certain
          sections, such as the new perpendicular taxiway areas, required treatment for soft
          ground. Site preparation, including soft ground treatment and compaction work,
          was carried out to ensure adequate bearing capacity for aircraft loads in each

          section.











































          170                                                                                                    The 30-year History of Incheon Airport Construction                                                                                                                                               171