Mar. 2023               Mar. 2024              May. 2024               Oct. 2024
              Opening of expanded     Completion of expanded   Designation of expanded   Completion of operational
              short-term parking at   cargo apron            Terminal 2 area and apron   readiness for expanded
              Transportation Center 2                        as airside              Terminal 2




                          Aug. 2023               Apr. 2024              May. 2024               Oct. 2024
                          Completion of remote    Completion of construction  Beginning of comprehensive  Completion of Phase 4
                          apron construction      of basic facilities for   commissioning for    construction project
                                                  Terminal 2 expansion   Terminal 2 expansion area