Key milestones of Incheon Airport’s Phase 4 construction project
Nov. 2017 Oct. 2019 June. 2021 Jan. 2022
Phase 4 master plan Ground-breaking and Opening of runway 4 for Installation of BHS for
revised (9th revision) piling work for Terminal 2 operations Terminal 2 expansion
expansion begins
Dec. 2018 Nov. 2020 Jan. 2022 Nov. 2022
Construction of Runway 4 Start of structural and Opening of northern Completion of roof steel
begins finishing work for remote apron for frame for Terminal 2
Terminal 2 expansion operations expansion