Key milestones of Incheon Airport’s Phase 4 construction project








              Nov. 2017               Oct. 2019              June. 2021              Jan. 2022
              Phase 4 master plan     Ground-breaking and    Opening of runway 4 for   Installation of BHS for
              revised (9th revision)  piling work for Terminal 2  operations         Terminal 2 expansion
                                      expansion                                      begins




                          Dec. 2018               Nov. 2020              Jan. 2022               Nov. 2022
                          Construction of Runway 4   Start of structural and   Opening of northern   Completion of roof steel
                          begins                  finishing work for     remote apron for        frame for Terminal 2
                                                  Terminal 2 expansion   operations              expansion